Separate capacity from earnings
A provider may have built a hall, signed a contract, delivered service on some cabinets, and reserved others for future use. Use a dated schedule for commercial availability, power capacity and billed usage by tenant. Collect the legal entity entitled to each payment and identify conditions that must be satisfied before revenue starts. Distinguish minimum commitments, availability fees, liquidated amounts, recurring charges, and usage-based earnings.
Understand capacity reallocation rights
Review whether the provider can move the tenant to another suite, campus, or third-party facility. Obtain a practical estimate for technologies that must be replicated, power and cooling requirements, data migration, testing and customer acceptance. A physical spare cabinet may not be suitable for a reserved service. For facilities context, the Department of Energy data center design guide covers environmental, cooling and power considerations that influence usable configuration.
Example — a damaged suite was contracted but unopened
A provider loses a portion of a hall to a physical event. Operational racks can move to an alternate hall. The unopened area cannot meet its scheduled service date because the replacement needs a different cooling configuration. Model the existing service expense separately from the future revenue delay and from any external contractual penalties. Show conditions on billing, alternative delivery rights, mitigation offers and the revised availability date.
Inputs for the broker and finance team
- Signed orders, phasing dates, payment triggers, and the flow of payments to insured entities.
- Engineering confirmation of available idle capacity and alternate location compatibility.
- Financial calculations with stated billing dates, variable expenses, and recovery assumptions.
Test which earning categories meet applicable business income or delay-in-startup definitions and how the applicable forms address alternate operations, mitigation expense and restoration periods. Use the actual forms and documented facts to estimate recoverable amounts.

Make the forecast usable after the incident
Keep the revenue model traceable to contracted and reasonably supportable expected occupancy by area. Record the latest date each reservation could convert to a service order and the conditions outside the facility operator's control. Segregate provider payments, installation charges, and income from occupying space or supplying power. A long-term commitment can increase the financial consequence of service delay while still containing legal conditions that must be satisfied before payment. Confirm any disclosed expectation is consistent across budgets, signed documents and submissions.
In another scenario, a partial outage leaves total square footage unchanged but reduces usable power below the amount promised to a customer. The parties agree to move some workloads elsewhere and credit part of the service charge. Record pre-event utilization, equipment and connection limits, approved corrective work, alternative charges and settlement terms. Distinguish the provider’s lost earnings from the tenant's loss and any contractual payment that merely reflects a commercial remedy. Evaluate whether a covered outage or gain in replacement revenue changes the figures, and identify which expenses instead represent upgrades unrelated to recovery.
Review implications of expanding a reservation
- Which restrictions on inventory substitution, alternative capacity or agreed use affect the recovery assumptions?
- Who keeps dated evidence of the facility milestone, signed contract, commercial start, and invoices when a customer disputes payment?
- How do property or delay terms treat revenue from space that has not yet entered service, separately from income at existing occupied facilities?
Provide the policy review with specific financial examples, replacement capacities and realistic alternatives. Separating the categories allows an insurer and finance team to identify what assumptions require documentation and what remains a commercial exposure.
Track whether new capacity is delivered under a binding addendum, informal forecast, or customer option. Confirm whether occupancy forecasts duplicate another open order for the same reserved space. Date and version the allocation so expected earnings can be reconstructed as of the relevant event.